Categories
Abolish Services (6)
Asset Protection (4)
Audio Distribution (7)
Bricks/bricklaying (42)
Building permit (11)
cabinetery (2)
carpentry (47)
color selection (18)
concrete (7)
Contract (42)
Council (31)
decking/alfresco (28)
demolition (29)
DLNA (3)
drafting (7)
electrical (3)
enviromental issues (27)
Family (13)
Finance (14)
fittings and fixtures (5)
flooring (3)
foundation/stumps (21)
Foxtel (1)
furniture (2)
garden (4)
HD Video (5)
heating/cooling (9)
insulation (6)
interior design (12)
landscaping (4)
man cave (8)
Onley Construction (3)
painting (1)
Phone (3)
Planning (96)
plaster (3)
plumbing (11)
Power (8)
Premier (36)
pretty pictures (3)
Prime Projects Construction (49)
Romeo Homes (33)
roof (15)
root barrier (5)
Site Preparation (100)
solar (1)
Uncategorized (104)
Utilities (15)
Video Distribution (5)
water tank/recycling (4)
weather (26)
windows (29)
WP Cumulus Flash tag cloud by Roy Tanck requires Flash Player 9 or better.
Project Milestones
- Place Deposit with Premier Builders:
1170 days ago - Change of Plan:
1097 days ago - Preliminary Building Agreement 1:
1065 days ago - Client Info Pack:
1032 days ago - Preliminary Plans:
973 days ago - House Demolition Day:
958 days ago - Received Final Contracts:
882 days ago - Bank Approval:
862 days ago - Contracts Signed:
851 days ago - Received Dispensation from council:
842 days ago - Root Barriers:
835 days ago - Block Excavated:
829 days ago - Applied for Planning Permit:
821 days ago - Prime Project Construction engaged:
728 days ago - Received Planning Permit:
712 days ago - Signed Contract with Prime and 5% deposit paid:
680 days ago - Building Permit Granted:
658 days ago - Block Set out:
656 days ago - Power being connected:
653 days ago - Water Meter moved and connected:
653 days ago - Sewage and Water being dug out:
653 days ago - Footings and slab:
628 days ago - Blindings spoil cleared:
625 days ago - Brickie Starting:
618 days ago - Concrete for piers poured:
615 days ago - Flooring Starts:
611 days ago - Framing Starts:
601 days ago - Roofing Starts:
586 days ago - Gutters and Facias Complete:
552 days ago - Solar Hot Water Panel Installed:
537 days ago - Roof Wrapped with Aircel:
530 days ago - Roofing Complete:
526 days ago - Some Windows Installed:
520 days ago - Security Data Cable Rough In:
469 days ago - Bricking - Stage 2 complete:
467 days ago - Upstairs Heating / Cooling Roughed In:
467 days ago - Lockup Chippies Start:
464 days ago - Last Windows Arrive:
446 days ago - Planned Lockup Date:
439 days ago - Start Plastering:
429 days ago - End Plastering:
425 days ago - Predicted Moving Day (Hopeful):
326 days ago
- Place Deposit with Premier Builders:
Archives
Minecraft
IP : Server is Offline
Category Archives: plaster
Oh what a beautiful weekend
We have been blessed with gorgeous weather this weekend, just perfect for getting an excavator onto the block! David spent Saturday with our friends Peter and Dave excavating the pad for the tank, all the post holes for the deck … Continue reading
cornice and chivas
We had been trying to catch up with our SS L last week but he was massively busy and hadn’t a chance to chat. Today we did catch up with him…and handed over the Chivas Regal we had been … Continue reading