Categories
Abolish Services (6)
Asset Protection (4)
Audio Distribution (5)
Bricks/bricklaying (38)
Building permit (7)
cabinetery (2)
carpentry (39)
color selection (17)
concrete (5)
Contract (42)
Council (30)
decking/alfresco (24)
demolition (29)
DLNA (3)
drafting (7)
electrical (1)
enviromental issues (26)
Family (12)
Finance (14)
fittings and fixtures (3)
flooring (1)
foundation/stumps (21)
Foxtel (1)
furniture (2)
garden (4)
HD Video (4)
heating/cooling (6)
insulation (3)
interior design (11)
landscaping (2)
man cave (8)
Onley Construction (3)
Phone (3)
Planning (96)
plumbing (11)
Power (8)
Premier (36)
pretty pictures (3)
Prime Projects Construction (48)
Romeo Homes (33)
roof (15)
root barrier (4)
Site Preparation (98)
solar (1)
Uncategorized (102)
Utilities (15)
Video Distribution (5)
water tank/recycling (4)
weather (26)
windows (29)
WP Cumulus Flash tag cloud by Roy Tanck requires Flash Player 9 or better.
Project Milestones
- Place Deposit with Premier Builders:
1173 days ago - Change of Plan:
1100 days ago - Preliminary Building Agreement 1:
1068 days ago - Client Info Pack:
1035 days ago - Preliminary Plans:
976 days ago - House Demolition Day:
960 days ago - Received Final Contracts:
885 days ago - Bank Approval:
865 days ago - Contracts Signed:
854 days ago - Received Dispensation from council:
845 days ago - Root Barriers:
838 days ago - Block Excavated:
832 days ago - Applied for Planning Permit:
824 days ago - Prime Project Construction engaged:
730 days ago - Received Planning Permit:
715 days ago - Signed Contract with Prime and 5% deposit paid:
683 days ago - Building Permit Granted:
661 days ago - Block Set out:
659 days ago - Power being connected:
656 days ago - Water Meter moved and connected:
656 days ago - Sewage and Water being dug out:
656 days ago - Footings and slab:
631 days ago - Blindings spoil cleared:
628 days ago - Brickie Starting:
621 days ago - Concrete for piers poured:
618 days ago - Flooring Starts:
614 days ago - Framing Starts:
604 days ago - Roofing Starts:
589 days ago - Gutters and Facias Complete:
555 days ago - Solar Hot Water Panel Installed:
540 days ago - Roof Wrapped with Aircel:
533 days ago - Roofing Complete:
529 days ago - Some Windows Installed:
523 days ago - Security Data Cable Rough In:
472 days ago - Bricking - Stage 2 complete:
470 days ago - Upstairs Heating / Cooling Roughed In:
470 days ago - Lockup Chippies Start:
467 days ago - Last Windows Arrive:
449 days ago - Planned Lockup Date:
442 days ago - Start Plastering:
432 days ago - End Plastering:
428 days ago - Predicted Moving Day (Hopeful):
329 days ago
- Place Deposit with Premier Builders:
Archives
Minecraft
IP : Server is Offline
Category Archives: water tank/recycling
getting tanked!
Going to be a quick one today after yesterdays novel. Arrived this morning to find concrete has been laid in the garage. Lovely young concreter and I spent a bit of time chatting while he waited for the concrete to … Continue reading
Understanding the need for a privacy fence
Have been busy at the block since our last post. David and Dave worked super hard to get the base of the deck in. We had hoped the water tank would be in place first but got the go ahead … Continue reading
Oh what a beautiful weekend
We have been blessed with gorgeous weather this weekend, just perfect for getting an excavator onto the block! David spent Saturday with our friends Peter and Dave excavating the pad for the tank, all the post holes for the deck … Continue reading
All tanked up!
On my way to see a friend today I dropped past the block and there was our SS and a great big black tank! The tank is going to sit flat under our deck, once they put the concrete slab … Continue reading